January 2026 Maintenance¶
COMPLETE: Planned Datacentre Outage – January 2026¶
.. meta::
:description: Planned datacentre outage impacting the Aoraki research compute cluster and hosted research services. :keywords: Aoraki, datacentre outage, maintenance, HPC, Open OnDemand, SLURM :Published: 16 December 2025
The Research Computing team advises users of a planned datacentre outage that will impact the Aoraki research compute cluster and several associated research services.
This outage is required to support scheduled electrical maintenance and will involve a complete power shutdown of the 325 Datacentre.
Outage Window¶
Important
Start: 12:00 pm, Friday 16 January 2026 End: 5:00 pm, Monday 19 January 2026 Timezone: NZDT
All systems hosted in the datacentre will be unavailable for the duration of this window.
Services Impacted¶
The following services will be unavailable during the outage:
- Aoraki high-performance compute cluster (login nodes and compute nodes)
- SLURM job scheduling and submission services
- Virtual machines hosted in the datacentre
- On-site storage services
- Web portals and research platforms hosted in the datacentre
- Departmental servers hosted in the datacentre
- Open OnDemand and hosted applications (including CryoSPARC)
What Users Need to Do¶
Warning
- Ensure all running jobs complete before the outage begins.
- Avoid scheduling long-running or critical workflows during this period.
- New SLURM job submissions will be disabled ahead of the outage.
- No user access or actions will be possible during the outage.
Users should plan workflows accordingly to avoid disruption.
What We Will Do¶
Research Computing team will:
- Drain the Aoraki cluster in advance of the outage.
- Perform a controlled shutdown of all affected systems.
- Coordinate with Facilities during the power outage.
- Restore services in a staged and validated manner once power is returned.
Service restoration will begin as soon as it is safe to do so after power is restored.